top of page

Construction Schedule

 

A schedule and a description of the approach for completing the project is provided below. The schedule includes a description of the approach and plan for executing the work in terms of how the site will be organized, how work will flow through the site, and how material will be managed. The schedule will clearly indicate all activities, durations, sequencing relationships, early and late dates, total and free float, and the critical path.

 

The complete assembly of the floor extension is planned to take 6 weeks to complete, with five, eight hour working days (Monday to Friday) per week. The project can start any time of the year, but it would be ideal for the work to be done during the spring or summer time, due to there being less delay from harsh weather conditions during that time. Also, at the start of each work day, a safety meeting will be held so that all personnel on site can perform their work safely. The detailed schedule with the duration of each phase is explained below.

 

A gantt chart regarding the Construction Schedule can be downloaded via the link below:

 

Construction Schedule (Excel)

 

Detailed Description of Activity

 

  1. Clear construction zone + set up protective measures - sectioning off and removing all furniture and objects within construction zone will take 4 hours, and setting up protective flooring and plastic tarps/sheets will also take 4 hours

  2. Mobilization + set up scaffolding - moving in construction equipment will take 4 hours and setting up scaffold will also take 4 hours, set everything up for deconstruction

  3. Disassemble wall, ceiling - deconstruct glass wall of meeting room to create space for second floor construction

  4. Disassemble railing - remove rail of the second floor hallway to create space for second floor construction

  5. Remove drywall - removing the dry wall that surrounds the perimeter of the walls to allow for installation of new beams, floors and walls, make sure area is clean and ready for installation of new floor

  6. Install 3 Douglas Fir beams - hoist and secure beams to existing columns to set up for floor installation

  7. Install floor joists + lay plywood subfloor - securing joists to beams will take 1 day, screwing subfloor on top of the joists will take half a day

  8. Construct new walls + install studs - construct the walls with openings for doors, installation of studs to frame partial height walls to allow for installation of new walls

  9. Install new walls - fixed to studs and screwed on to floor, set up area for installation of windows and glass walls

  10. Install exterior windows - cutting openings in exterior walls will take 1 day, installing the vinyl windows will take 1 day

  11. Construct + install glass enclosure wall - glass company checks space to make sure the glass walls will fit in the openings, and then install the glass walls, set up for interior finishes

  12. Install lighting - install lights and electrical systems to first and second floors

  13. Electrical + gas line installation - setting up phone and internet connections will take 1 day, setting up gas line, filter and fireplace on second floor will take 1 and a half days

  14. Insulate + drywall + paint walls - installing fibreglass between wall studs will take 1 day, drywall installation, painting walls and setting up for floor installation will take 1 and a half days

  15. Lay engineered hardwood floor - installing engineered floor over subfloorInstall doors + partition walls - installation of partition walls to allow separation of rooms

  16. Install doors + partition walls - Putting in the door frame and installing the doors and handles. As well as installation of Skywall (partition) onto douglas fir beams.

  17. Demobilization + clean up - clean up entire area, move out all equipment and excess materials, set up furniture and other objects and the new Mount Pleasant will be ready for use

 

Approximate Time Allocation

Regarding Various Activities

 

  1. Clear construction zone + set up protective measures - 1 day

  2. Mobilization + set up scaffolding - 1 day

  3. Disassemble wall, ceiling - 1 day

  4. Disassemble railing - 1 day

  5. Remove drywall - 2 days (week 1)

  6. Install 3 Douglas Fir beams - 1 day

  7. Install floor joists + lay plywood subfloor - 1.5 days

  8. Construct new walls + install studs - 1.5 days (week 2)

  9. Install new walls - 3 days

  10. Install exterior windows - 2 days (week 3)

  11. Construct + install glass enclosure wall - 3 days

  12. Install lighting - 2 days (week 4)

  13. Electrical + gas line installation - 2.5 days

  14. Insulate + drywall + paint walls - 2.5 days (week 5)

  15. Lay engineered hardwood floor - 1.5 days

  16. Install doors + partition walls - 1.5 days

  17. Demobilization + clean up - 2 days (week 6)

Early Dates and Late Dates:

 

Early

 

  1. Clear construction zone + set up protective measures - ES = Apr 30, EF = Apr 30

  2. Mobilization + set up scaffolding - ES = May 1, EF - May 1

  3. Disassemble wall, ceiling - ES = May 4, EF = May 4

  4. Disassemble railing - ES = May 5, EF = May 5

  5. Remove drywall - ES = May 6, EF = May 7

  6. Install 3 Douglas Fir beams - ES = May 8, EF = May 8

  7. Install floor joists + lay plywood subfloor - ES = May 11, EF = May 12

  8. Construct new walls + install studs - ES = May 12, EF = May 13

  9. Install new walls - ES = May 14, EF = May 18

  10. Install exterior windows - ES = May 19, EF = May 20

  11. Construct + install glass enclosure wall - ES = May 21, EF = May 25

  12. Install lighting - ES = May 26, EF = May 27

  13. Electrical + gas line installation - ES = May 28, EF = Jun 1

  14. Insulate + drywall + paint walls - ES = June 1, EF = June 3

  15. Lay engineered hardwood floor - ES = June 4, EF = June 5

  16. Install doors + partition walls - ES = June 5, EF = June 8

  17. Demobilization + clean up - ES = June 9, ES = June 10

 

Late

 

  1. Clear construction zone + set up protective measures - LS = May 6, LF = May 6

  2. Mobilization + set up scaffolding - LS = May 7, LF = May 7

  3. Disassemble wall, ceiling - LS = May 8, LF = May 8

  4. Disassemble railing - LS = May 11, LF = May 11

  5. Remove drywall - LS = May 12, LF = May 13

  6. Install 3 Douglas Fir beams - LS = May 14, LF = May 14

  7. Install floor joists + lay plywood subfloor - LS = May 15, LF = May 18

  8. Construct new walls + install studs - LS = May 18, LF = May 19

  9. Install new walls - LS = May 20, LF = May 22

  10. Install exterior windows - LS = May 25, LF = May 26

  11. Construct + install glass enclosure wall - LS = May 27, LF = May 29

  12. Install lighting - LS = June 1, LF = June 2

  13. Electrical + gas line installation - LS = June 3, LF = June 5

  14. Insulate + drywall + paint walls - LS = June 5, LF = June 9

  15. Lay engineered hardwood floor - LS = June 10, LF = June 11

  16. Install doors + partition walls - LS = June 11, LF = June 12

  17. Demobilization + clean up - LS = June 15, LF = June 16

 

Float:

 

Lag

 

  1. Lag (1,2) = 1 day

  2. Lag (2,3) = 1 day

  3. Lag (3,4) = 1 day

  4. Lag (4,5) = 1 day

  5. Lag (5,6) = 1 day

  6. Lag (6,7) = 1 day

  7. Lag (7,8) = 0 days

  8. Lag (8,9) = 1 day

  9. Lag (9,10) = 1 day

  10. Lag (10,11) = 1 day

  11. Lag (11,12) = 1 day

  12. Lag (12,13) = 1 day

  13. Lag (13,14) = 0 days

  14. Lag (14,15) = 1 day

  15. Lag (15,16) = 0 days

  16. Lag (16,17) = 1 day

 

Total Float

 

  1. Clear construction zone + set up protective measures - TF (1) = 4 days

  2. Mobilization + set up scaffolding - TF (1) = 4 days

  3. Disassemble wall, ceiling - TF (1) = 4 days

  4. Disassemble railing - TF (1) = 4 days

  5. Remove drywall - TF (1) = 4 days

  6. Install 3 Douglas Fir beams - TF (1) = 4 days

  7. Install floor joists + lay plywood subfloor - TF (1) = 4 days

  8. Construct new walls + install studs - TF (1) = 4 days

  9. Install new walls - TF (1) = 4 days

  10. Install exterior windows - TF (1) = 4 days

  11. Construct + install glass enclosure wall - TF (1) = 4 days

  12. Install lighting - TF (1) = 4 days

  13. Electrical + gas line installation - TF (1) = 4 days

  14. Insulate + drywall + paint walls - TF (1) = 4 days

  15. Lay engineered hardwood floor - TF (1) = 4 days

  16. Install doors + partition walls - TF (1) = 4 days

  17. Demobilization + clean up - TF (1) = 4 days

bottom of page